Faced with a failing pump station and a tight federal funding deadline, Big Beaver Borough, PA, needed a fast, reliable solution after previous replacement efforts stalled. A complete EveraFLOTM pump station package was delivered—streamlining permitting, approvals, and installation. The result: on-time, cost-effective implementation that overcame delays common to traditional construction methods.
Big Beaver Borough
Beaver County, Pennsylvania
October 2024
| EveraFLO 93” | |
|---|---|
| Avg Daily Flow | 90,000 GPD |
| Discharge Rate | 250 GPM |
| Pump Type | Duplex Submersible (Grinder) |
| Wetwell Depth | 25’ |
Packaged municipal station delivered as a coordinated replacement solution.
Share flow targets and site constraints—our team will recommend an EveraFLO configuration aligned with permitting and constructability.