EveraFLO Case Study

Greenfield Township – Pump Stations

Lackawanna County, PA

The Route 106 and Route 247 stations were at the end of their service life and critical to the reliability of the township’s wastewater system. Our turnkey, factory-built solutions ensured fast installation, reduced on-site construction time, and long-term durability. The completed project reflects a cost-effective, low-disruption approach to modernizing essential public infrastructure.

Greenfield Township EveraFLO wastewater pump station case study

Greenfield Township pump stations (Route 106 site).

Owner

Greenfield Township Sewer Authority

Location

Lackawanna County, Pennsylvania

Installation Date

August 2024

Scope of Supply

  • EveraFLO 84” Dia. Municipal Pump Station (Route 106)
  • EveraFLO 84” Dia. Municipal Pump Station (Route 247)
  • Aluminum Access Hatch Covers
  • Triplex & Duplex Pump Assemblies
  • External Valve Vault Assemblies
  • Remote Control & Monitoring
  • Installation & Commissioning Support

Technical Data

EveraFLO 84” (Route 106) EveraFLO 84” (Route 247)
Avg Daily Flow 19,050 GPD 19,050 GPD
Discharge Rate 180 GPM 205 GPM
Pump Type Duplex Wilo 10 HP
(Submersible • Grinder)
Duplex Wilo 10 HP
(Submersible • Grinder)
Wetwell Depth 14’ 14’

Two coordinated packaged municipal stations delivered for fast installation and long-term reliability.

Need a budgetary configuration or basis-of-design?

Share flow targets and site constraints—our team will recommend an EveraFLO configuration aligned with permitting and constructability.

A next-generation engineering and manufacturing company delivering innovative equipment and infrastructure products for the water, wastewater, and energy storage utility markets.

© 2026 Infrastructure Dynamics. All rights reserved.